Construction Updates
See Advisory Statement for important information related to the climate and sustainability content on this website.
Safety
Safety is our number one value and is fundamental to what we do.
The safety of the communities we operate in, our employees and the environment we live and work in is paramount. As a leading North American energy infrastructure company, our experience in building major export facilities off the West-Coast helps drive continued progress while being anchored by safety.
As AltaGas and Vopak partners to build this critical project, the teams on the ground stay committed to getting the project done, safely and reliably.
Stay Informed
As progress on the REEF project continues to roll out, we are committed to keeping our stakeholders and right holders up-to-date on project construction on a monthly basis.
Construction progress: September 28, 2026
September 28, 2026
OPTI 1 construction update:
- Foundation installation continues to progress as planned in the Uplands area
- Mechanical Contractor installing spools into existing REEF pipe rack
REEF construction update:
Uplands:
- Mechanical Contractor progressing well and on track to substantially complete scope in coming weeks.
- Electrical & Instrumentation continue to achieve good progress on electrical scope
- Pre-Commissioning is underway
Rail, Road and Utilities Corridor (RRUC):
- Rail contractor continuing with 2nd and final phase of construction
Jetty Updates:
- Piers 1 through 12: Completed
- Trestle Spans:Completed setting 1 through 13 on piers and continuing with connections
- Loading Platform:
- LP-01/02/03/04: Piers completed to allow main platform setting
- Set Main Platform on Piers (LP-01-04) Sept 25
- Construction is now focused on completing the Main Platform connections
- Protection Dolphins PD-1 and PD2: preparing to install falseworks
- Port Entry Light: completing design / fabrication of the falseworks prior to installation
- Continued interconnect pipe welding between the Trestle Spans (Spans 1-10 complete)
Asian Fabrication Status:
- Main Platform section, suction anchors, and initial mooring chains delivered Sept 12
Remaining Mooring chain section ready to ship
Watson Island Camp (near Port Edwards):
- Continue to manage capacity to ensure all workforce stays in camp
- Avoiding alternate arrangements in town where possible
- Some crews needing to stay in town when camp capacity reached
Night Activities:
- AltaGas continued with some night shift activities for marine Jetty construction.
- Restart Date: July 2026
- Forecast End Date: Dec 2026 (will assess need to continue at year end)
- Best efforts will be made to minimize potential noise and light impacts.
- Activity: Drilling, welding and scaffolding activities
Questions: Contact us
Construction progress: Aug 26, 2026
August 26, 2026
OPTI 1 construction update:
- Foundation installation continues to progress as planned in the Uplands area
- Mechanical Contractor installing spools into existing REEF pipe rack
REEF construction update:
Uplands:
- Modules and equipment at site and setting complete
- Mechanical Contractor progressing well and on track to substantially complete scope in coming weeks. We will be starting pre-commissioning of systems.
- Electrical & Instrumentation continue to achieve good progress on electrical scope
- Field erected building scope has demobilized from site.
Rail, Road and Utilities Corridor (RRUC):
- Rail offload modules, loading arms, and gangway is complete
- Rail contractor continuing with 2nd and final phase of construction.
Jetty Updates:
- Piers 1 through 12: Completed
- Trestle Spans 1 through 13 set on piers
- Loading Platform:
- LP-01/03: Pile cap welding complete; ready for grouting
- LP-02/04: Concrete now complete, pile cut, cap, and grouting progressing
- LP-05/06/07/08: Piers completed
- Set Transition Platform set on Piers (LP-05-08) July 20-27
- Construction is now focused on completing the Main Platform at Piers LP-01 thru LP-04
- Main Platform will arrive at the end of Aug / early Sept to set on Piers LP-01-04
- Continued interconnect pipe welding between the Trestle Spans (Spans 1-10 complete)
Asian Fabrication Status:
- Main Platform section & suction anchors in final stages of fabrication
- Loadout mid-August with expected arrival in late August / early Sept.
Watson Island Camp (near Port Edwards):
- Continue to manage capacity to ensure all workforce stays in camp avoiding alternate arrangements in town where possible
Night Activities:
- AltaGas continued with some night shift activities for marine Jetty construction.
- Restart Date: July 2026
- Forecast End Date: August 2026
- Best efforts will be made to minimize potential noise and light impacts.
- Activity: Drilling, welding and scaffolding activities
Questions: Contact us
Construction progress: July 27, 2026
July 27, 2026
OPTI 1 construction update:
- Excavation for process foundations complete
- Commence foundation work
REEF construction update:
Uplands:
- Majority of modules and equipment at site and setting complete
- Mechanical Contractor making good progress on structural and piping interconnect installation
- Electrical & Instrumentation achieving good progress on electrical scope
- Field erected building scope is also making good progress
Rail, Road and Utilities Corridor (RRUC):
- Rail offload modules, loading arms, and gangway is majority complete
- Rail contractor getting ready to mobilize in July for the second phase of construction to begin
- Blasting in ERRUC successfully completed and crushing is ongoing
Jetty Updates:
- Piers 1 through 12: Completed
- Trestle Spans 1 through 12 set on piers
- Loading Platform:
- LP-01/03: Pile cap welding complete; ready for grouting
- LP-02/04: Rock Socket in progress
- LP-05/06/07/08: Piers completed
- Construction is now focused on completing the Main Platform at Piers LP-01 thru LP-04
- Main Platform to arrive at the end of August and then set on Piers LP-01-04
- Continued interconnect pipe welding between the Trestle Spans (Spans 1-10 complete)
- Set Transition Platform set on piers (LP-05-08) July 20-27
Asian Fabrication Status:
- Main Platform section & suction anchors in final stages of fabrication; loadout early August
Watson Island Camp (near Port Edwards):
- Completed remediation and replacement post fire incident from January 2
- Temporary facilities were brought in January to lessen burden on surrounding communities
- Replacement facilities now operational
Night Activities:
- AltaGas continued with some night shift activities for marine Jetty construction
- Plan to Restart Date: July 2026
- End Date: August 2026
- Best efforts will be made to minimize potential noise and light impacts
- Activity: Drilling, welding and scaffolding activities
Questions: Contact us
© 2026 Ridley Island Energy Export Facility Limited Partnership. All Rights Reserved. | Last update: 2026_09_28

