Construction Updates
See Advisory Statement for important information related to the climate and sustainability content on this website.
Safety
Safety is our number one value and is fundamental to what we do.
The safety of the communities we operate in, our employees and the environment we live and work in is paramount. As a leading North American energy infrastructure company, our experience in building major export facilities off the West-Coast helps drive continued progress while being anchored by safety.
As AltaGas and Vopak partners to build this critical project, the teams on the ground stay committed to getting the project done, safely and reliably.
Stay Informed
As progress on the REEF project continues to roll out, we are committed to keeping our stakeholders and right holders up-to-date on project construction on a monthly basis.
Construction progress: May 27, 2026
May 27, 2026
OPTI 1 construction update:
- Drilling/Blasting complete in Uplands
- Ongoing site grading/drainage/roads
REEF construction update:
Uplands:
- 259 modules and equipment successfully set; ~93% to date
- Mechanical Contractor making good progress on structural and piping interconnect installation
- Electrical & Instrumentation achieving good progress on electrical scope
- Field erected building scope is also making good progress
Rail, Road and Utilities Corridor (RRUC):
- Rail offload modules, loading arms, and gangway installation progressing well. Roof installation nearing completion
- Rail contractor successfully completed the first phase of construction, CN inspection successfully completed for departure track in April. Second phase of construction to begin in the second half of 2026
- Installation Power poles complete for this phase, E&I contractor making good progress on cable installation
- Blasting in ERRUC successfully completed and crushing is ongoing
Jetty Updates:
- Piers 1 through 12: Completed; Span 1 through 8 set on piers
- Loading Platform:
- LP-03: Temporary falseworks piles installed
- LP-04: Rock Socket in progress
- LP-05: Rock socket complete
- LP-6: Rock Socket & concrete infill complete
- LP-7/8: Rock Socket & concrete infill complete
- Construction now focused on completing the Transition Platform at Piers LP-5 to 8
- Started the interconnect pipe welding between the Trestle Spans
- Set Trestle Span 9, 10, 11, and the corner module in May 7-9
Asian Fabrication Status:
- Remaining 2 Accumulators and final modules arrived in Prince Rupert Feb 28.
- All Accumulators are installed on their foundations, and the pipe rack and bridge modules were set as planned.
Marine Offloading Facility (MOF):
- Fifth and final shipment: Firewater Pumphouse module arrived and offloaded April 28.
Watson Island Camp (near Port Edwards):
- Completed remediation and replacement post fire incident from Jan 2
- Temporary facilities were brought in January to lessen burden on surrounding communities
- Replacement facilities now operational
Night Activities:
- AltaGas continued with some night shift activities for marine Jetty construction.
- Restarted Date: April 2026
- End Date: July 2026
- Best efforts will be made to minimize potential noise and light impacts.
- Activity: Welding and scaffolding activities
Questions: Contact us
Construction progress: April 29, 2026
April 29, 2026
Optimization One construction update:
- Drilling/Blasting/Crushing scope ongoing in Uplands to support site grading
REEF construction update:
Uplands:
- Concrete foundations are complete
- 197 modules and equipment successfully set; ~92% to date
- Mechanical Contractor making good progress on structural and piping interconnect installation
- Electrical & Instrumentation achieving good progress on electrical scope
- Field erected building scope is ongoing
Rail, Road and Utilities Corridor (RRUC):
- Rail offload modules loading arm and gangway installation progressing well
- Rail contractor successfully completed first phase of construction, second phase to begin in second half of 2026
- Power poles complete for this phase, E&I contractor making good progress on cabling
- Blasting in ERRUC successfully completed and crushing is ongoing
Jetty Updates:
- Piers 1 through 12: Completed; Span 1 through 8 set on piers
- Pier 11: Ready for Concrete Infill
- Pier 12: Complete and ready for turnover to ALA
- Loading Platform:
- LP-03: Temporary falseworks piles installed
- LP-04: Piles installed; ready for Rock Socket
- LP-05: Permanent piles stacked
- LP-6: Permanent piles installed and ready for Rock Socket
- LP-7/8: Permanent piles installed and ready for Rock Socket
- Construction focus on completing Transition Platform Piers LP-5-8
- Started interconnect pipe welding between the Trestle Spans
- Preparing to set Trestle Span 9 –10 early May
Asian Fabrication Status:
- Remaining 2 Accumulators and final modules arrived in Prince Rupert Feb 28.
- All Accumulators are installed on foundations and modules set as planned.
Marine Offloading Facility (MOF):
- Fifth and final shipment: Firewater Pumphouse module arrived and offloaded April 28.
Watson Island Camp (near Port Edwards):
- Progress made on remediation and replacement post fire incident from Jan 2.
- Temporary facilities brought in January to lessen burden on surrounding communities.
- Replacement facilities on schedule to be operational by end of Feb / 1st week in March.
Night Activities:
- AltaGas continued with some night shift activities for marine Jetty construction.
- Restarted Date: April 2026
- End Date: July 2026
- Best efforts will be made to minimize potential noise and light impacts.
- Activity: Welding and scaffolding activities.
- Questions: Contact us
Construction progress: March 27, 2026
March 27, 2026
Optimization One Projectconstruction updates:
- Foundation formwork and pours ongoing in Uplands area
REEF construction update:
Uplands:
- Completing concrete foundations
- 110 modules successfully set; ~81% of modules set to date
- Mechanical Contractor making good progress on setting modules and equipment
- Electrical & Instrumentation achieving good progress on electrical scope
- Field erected building scope is ongoing
Rail, Road and Utilities Corridor (RRUC):
- Rail offload modules all received at site and set in position
- Rail contractor finalizing track surfacing
- E&I contractor making good progress on standing power poles
- Blasting in ERRUC commencing March 24 and expected to last through April
Jetty Updates:
- Piers 1 through 10: Completed; Span 1 through 8 set on piers
- Pier 11: Ready for Concrete Infill
- Pier 12: Complete and ready for turnover to ALA
- Loading Platform:
- LP-03: Temporary falseworks piles installed
- LP-04: Piles installed; ready for Rock Socket
- LP-05: Permanent piles stacked
- LP-6: Permanent Piles installed and ready for Rock Socket
- LP-7/8: Permanent piles installed and ready for Rock Socket
- Crane Boom salvage complete and ROV seabed scan seabed confirmed no further debris
- Construction focus on completing Pier 11 and Loading Platform Piers 5-8
- Continued with Trestle Span module interconnect bolt-up activity
Asian Fabrication Status:
- Remaining 2 Accumulators and final interconnecting modules in Prince Rupert Feb 28
- Accumulators installed on foundations, modules offloaded, and being set as planned
Marine Offloading Facility (MOF):
- Fifth and final shipment: Firewater Pumphouse module planned to arrive late April
Watson Island Camp (near Port Edwards):
- Progress made on remediation and replacement post fire incident from Jan 2
- Temporary facilities brought in January to lessen burden on surrounding communities
- Replacement facilities on schedule to be operational by end of Feb / 1st week in March
Night Activities:
- AltaGas continued with some night shift activities for marine Jetty construction
- Restart Date: April 2026
- End Date: July 2026
- Best efforts will be made to minimize potential noise and light impacts.
- Activity: Welding and scaffolding activities
Questions: Contact us
© 2026 Ridley Island Energy Export Facility Limited Partnership. All Rights Reserved. | Last update: 2026_05_27

