Construction Updates
See Advisory Statement for important information related to the climate and sustainability content on this website.
Safety
Safety is our number one value and is fundamental to what we do.
The safety of the communities we operate in, our employees and the environment we live and work in is paramount. As a leading North American energy infrastructure company, our experience in building major export facilities off the West-Coast helps drive continued progress while being anchored by safety.
As AltaGas and Vopak partners to build this critical project, the teams on the ground stay committed to getting the project done, safely and reliably.
Stay Informed
As progress on the REEF project continues to roll out, we are committed to keeping our stakeholders and right holders up-to-date on project construction on a monthly basis.
Construction progress: Nov 26, 2026
November 26, 2026
OPTI 1 construction update:
- Foundation installation continues to progress as planned in the Uplands area
Mechanical Contractor continue installing spools into existing REEF pipe rack
Modules being set in Uplands
REEF construction update:
Uplands:
- Mechanical and Electrical & Instrumentation contractors progressing final turnover to CSU team
Pre-Commissioning continues to progress well
Rail, Road and Utilities Corridor (RRUC):
- Rail contractor complete construction and working on turnover
Jetty Updates:
- Continued paint touch ups between the Trestle Spans and platform structures
- Piers 1 through 12: Piling complete and removing falseworks as conditions allow
- Trestle Spans: Completed connections on all 13 piers
Loading Platform:
- Construction is now focused on completing the Main Platform connections
- Loading arms, fire water monitor towers, gangway all set on the main platform
- Mechanical: Complete welding piping and started hydrotest program
Elec & Instrumentation: Started preparing for MCC setting and cable pulling - Protection Dolphins PD-1 and PD2:
- PD-1: Falseworks 50% installed and starting to install header beams
- PD-2: Falseworks 100% installed, ready to start permanent pile installation
- Port Entry Light: Completed pile fabrication and installation
- Next will plan installation of the platform and tower
- Mooring Anchor Piles:
- 5 Anchors received and prepped for installation.
- Temporary anchors set in position
- DB General now on site and preparing for installation of the main anchor piles
Asian Fabrication Status:
-
- Balance of mooring chain now in transit to Prince Rupert with the OPTI 1 Bullet.
Watson Island Camp (near Port Edwards):
-
- Continue to manage camp while at capacity to ensure all workforce stays in camp
- Avoiding alternate arrangements in town when possible
- Some crews needing to stay in town when capacity exceeded
Night Activities:
-
- AltaGas continued with some night shift activities for marine Jetty construction.
- Forecast End Date: Dec 2026 (will assess need to continue at year end)
- Best efforts will be made to minimize potential noise and light impacts.
- Activity: Drilling, welding, and scaffolding activities
- AltaGas continued with some night shift activities for marine Jetty construction.
Questions: Contact us
Construction progress: October 27, 2026
October 27, 2026
OPTI 1 construction update:
- Foundation installation continues to progress as planned in the Uplands area
- Mechanical Contractor installing spools into existing REEF pipe rack
- Modules starting to show up on-site for install
REEF construction update:
Uplands:
- Mechanical and Electrical & Instrumentation contractors progressing on system completion, walkdowns, and Construction Completion milestones
- Pre-Commissioning is underway and achieving good progress
Rail, Road and Utilities Corridor (RRUC):
- Rail contractor wrapping up final stages of 2nd and final phase of construction
Jetty Updates:
- Piers 1 through 12: Completed
- Trestle Spans:Completed setting 1 through 13 on piers and continuing with connections
- Loading Platform:
- LP-01/02/03/04: Piers completed to allow main platform setting
- Set Main Platform on Piers (LP-01 to 04) Sept 25
- Construction is now focused on completing the Main Platform connections
- Protection Dolphins PD-1 and PD2: preparing to install falseworks
- Port Entry Light: completing design / fabrication of the falseworks prior to installation
- Continued interconnect pipe welding between the Trestle Spans (Spans 1-10 complete)
Asian Fabrication Status:
- Main Platform section, suction anchors, and initial mooring chains delivered Sept 12
- Remaining Mooring chain section ready to ship
Watson Island Camp (near Port Edwards):
- Continue to manage capacity to ensure all workforce stays in camp
- Avoiding alternate arrangements in town where possible
- Some crews needing to stay in town when camp capacity reached
Night Activities:
- AltaGas continued with some night shift activities for marine Jetty construction.
- Restart Date: July 2026
- Forecast End Date: Dec 2026 (will assess need to continue at year end)
- Best efforts will be made to minimize potential noise and light impacts
- Activity: Drilling, welding and scaffolding activities
Questions: Contact us
Construction progress: September 28, 2026
September 28, 2026
OPTI 1 construction update:
- Foundation installation continues to progress as planned in the Uplands area
- Mechanical Contractor installing spools into existing REEF pipe rack
REEF construction update:
Uplands:
- Mechanical Contractor progressing well and on track to substantially complete scope in coming weeks.
- Electrical & Instrumentation continue to achieve good progress on electrical scope
- Pre-Commissioning is underway
Rail, Road and Utilities Corridor (RRUC):
- Rail contractor continuing with 2nd and final phase of construction
Jetty Updates:
- Piers 1 through 12: Completed
- Trestle Spans:Completed setting 1 through 13 on piers and continuing with connections
- Loading Platform:
- LP-01/02/03/04: Piers completed to allow main platform setting
- Set Main Platform on Piers (LP-01-04) Sept 25
- Construction is now focused on completing the Main Platform connections
- Protection Dolphins PD-1 and PD2: preparing to install falseworks
- Port Entry Light: completing design / fabrication of the falseworks prior to installation
- Continued interconnect pipe welding between the Trestle Spans (Spans 1-10 complete)
Asian Fabrication Status:
- Main Platform section, suction anchors, and initial mooring chains delivered Sept 12
Remaining Mooring chain section ready to ship
Watson Island Camp (near Port Edwards):
- Continue to manage capacity to ensure all workforce stays in camp
- Avoiding alternate arrangements in town where possible
- Some crews needing to stay in town when camp capacity reached
Night Activities:
- AltaGas continued with some night shift activities for marine Jetty construction.
- Restart Date: July 2026
- Forecast End Date: Dec 2026 (will assess need to continue at year end)
- Best efforts will be made to minimize potential noise and light impacts.
- Activity: Drilling, welding and scaffolding activities
Questions: Contact us
© 2026 Ridley Island Energy Export Facility Limited Partnership. All Rights Reserved. | Last update: 2026_11_27

