Construction Updates
See Advisory Statement for important information related to the climate and sustainability content on this website.
Safety
Safety is our number one value and is fundamental to what we do.
The safety of the communities we operate in, our employees and the environment we live and work in is paramount. As a leading North American energy infrastructure company, our experience in building major export facilities off the West-Coast helps drive continued progress while being anchored by safety.
As AltaGas and Vopak partners to build this critical project, the teams on the ground stay committed to getting the project done, safely and reliably.
Stay Informed
As progress on the REEF project continues to roll out, we are committed to keeping our stakeholders and right holders up-to-date on project construction on a monthly basis.
Construction progress: November 18, 2025
November 18, 2025
Optimization One construction updates:
Optimization 1 Project:
- Civil earthworks has commenced (tree clearing, overburden removal)
Initial construction build out updates:
Uplands:
- Continue concrete foundations work
- Mechanical Contractor making good progress on setting modules and equipment
- Electrical & Instrumentation Contractor work ongoing
- Achieving good progress on field erected buildings
Rail, Road and Utilities Corridor (RRUC):
- Rail contractor will return in mid-2026 to complete
Jetty Updates:
- Pier 1: Completed; Span 1 set
- Pier 2: Completed; Span 2 set
- Pier 3: Completed; Span 3 set
- Pier 4: Completed; Span 4 set
- Pier 5: Completed; Span 5 set
- Pier 6: Completed; Span 6 set
- Pier 7: Turned over to AltaGas
- Pier 8: Turned over to AltaGAs
- Pier 9: Ready for concrete infill
- Pier 10: Concrete infill in progress
- Pier 11: Ready for Rock socket
- Pier 12: Permanent piles stacked
- Loading Platform:
- LP-03: Temporary falseworks piles installed
- LP-04: Falseworks piles and frame installed
- LP-05: Permanent piles stacked
- LP-6: Permanent Piles stacked
- LP-7/8: Permanent piles stacked and sealed
- Trestle Module Spans 3 and 6 set in place at the end of October
Asian Fabrication Status:
- REEF’s LPG Accumulators and Bullets and more modules arrived November 15; off loading in progress
Marine Offloading Facility (MOF):
- Continues to be used for offloading marine shipments as they arrive
- Third ship has docked at the MOF and currently unloading the first Accumulator, 2 Bullets, and some more modules from Asia
Night Activities:
- AltaGas continued with some night shift activities for marine jetty construction.
- Start Date: October 24, 2025
- End Date: June 2026
- Best efforts will be made to minimize potential noise and light impacts.
- Activity: Additional activities will include drilling, welding and scaffolding activities .
- Questions: Contact us
Construction progress: October 18, 2025
October 18, 2025
Updated November 6, 2025
Uplands:
- Continue rock placement and foundation backfilling
- Continue concrete foundations work
- Mechanical Contractor continuing work on setting modules and equipment
- Electrical & Instrumentation Contractor awarded and scope to begin ramping up at site
- Achieving good progress on field erected buildings
- Additional tree clearing activity will start on November 10 and will occur for approximately 4-6 weeks
Rail, Road and Utilities Corridor (RRUC):
- Rock crushing completed on available material
- Rail construction will wrap up 2025 work in Q3 and return in mid-2026 to complete
Jetty Updates:
- Pier 1: Completed; Span 1 set
- Pier 2: Completed; Span 2 set
- Pier 3: Turned over to AltaGas
- Pier 4: Turned over to AltaGas
- Pier 5: Turned over to AltaGas
- Pier 6: Turned over to AltaGas
- Pier 7: Turned over to AltaGas
- Pier 8: Grout complete
- Pier 9: One rock socket remaining
- Pier 10: One rock socket remaining
- Pier 11: Ready for Rock socket
- Pier 12: Permanent piles stacked
- Loading Platform:
- LP-7/8: Permanent piles stacked and sealed
- LP-6: Permanent Piles stacked
- LP-5: Falseworks piles and frame installed
- LP-4: Falseworks piles and frame installed
- Trestle Module Spans 3 and 6 will be delivered to site by the end of October
Marine Offloading Facility (MOF):
- Ready to receive next shipments
- Second ship has docked at the MOF and currently unloading 43 modules from Asia
Asian Fabrication Status:
- REEF’s LPG Accumulators and Bullets for the project are complete and are projected to start arriving onsite in 1st week in November
Night Activities:
- AltaGas will be commencing with some additional night shift activities for marine jetty construction.
- Best efforts will be made to minimize potential noise and light impacts.
- Start Date: October 24, 2025
- End Date: June 2026
- Activity: Additional activities will include drilling. Welding and scaffolding activities will continue.
- Questions: Contact us
Construction progress: September 18, 2025
September 18, 2025
Uplands:
- Continue rock placement and foundation backfilling
- Continue concrete foundations work
- Includes main plant area and interconnecting pipe rack foundations and Jetty
- Finalizing installation of underground Firewater and Electrical facilities
- Mechanical Contractor has mobilized and off to strong start setting modules and equipment
- Cold Storage building has been erected and work continues on the Warehouse and Office / Control Room buildings
Rail, Road and Utilities Corridor (RRUC):
- Continue with rock crushing and placement
- Continue with culvert and manhole install
- Rail construction is progressing on schedule as planned
Jetty Updates:
- Pier 1: Completed grout and ready to receive Trestle Span 1
- Pier 2: Completed grout and ready to receive Trestle Span 2
- Pier 3: Ready for grout
- Pier 4: Completed grout and ready for preparation of Trestle install
- Pier 5: Completed grout and ready for preparation of Trestle install
- Pier 6: Continue with rock socket drilling
- Pier 7: Permanent piles installed, ready for rock socket drilling
- Pier 8: Permanent piles installed, ready for rock socket drilling
- Pier 9: Ready for permanent pile cap install
- Pier 10: Drilling final permanent piles
- Pier 11: Ready for rock socket drilling
- Pier 12: Ready for rock socket drilling
- Loading Platform:
- LP-4: Falseworks piles/frame installed; prepping for permanent jacket install
- LP-6: Permanent piles installed; ready for rock socket
- LP-7/8: Permanent piles installed; ready for rock socket
- Trestle Module Spans 1 and 2 delivered and set into place September 3-6
- Offloaded last marine vessel load of remaining loading platform piles and jacket
Marine Offloading Facility (MOF):
- Completed installation of RRUC to MOF access ramp
- Wharf construction completed (by PRPA)
- First use was early September with the offloading of the Trestle span 1 and piperack modules for the Uplands area
- Asian fabrication status:
- REEF’s LPG Accumulators and Bullets for the project are 80% complete and are projected to start arriving onsite in October
- Interconnect pipe rack module fabrication is progressing per plan
- First shipment arrived early September with the second shipment in transit
Night activities:
- Night activities include water management, fueling, rock breaking on the west Rail, Road Utility Corridor and Uplands foundation backfill, and welding on the Jetty piers
- No active night drilling activities are occurring at night on site
Dust control:
- We are committed to maintaining safe on-site conditions that adhere to best practices
- We use freshwater for on-site road dewatering, to manage dust exposure and minimize impacts to the community
Port Edward Harbour Usage:
- Beginning mid-September, there will be an increase in traffic at the Port Edward Marina early in the morning and end of the day as four vessels will transport employees from Marina to the Jetty for work on the piers and loading platform. This will also result in more vehicles in parking areas.
© 2025 Ridley Island Energy Export Facility Limited Partnership. All Rights Reserved. | Last update: 2025_11_20

