Construction Updates
See Advisory Statement for important information related to the climate and sustainability content on this website.
Safety
Safety is our number one value and is fundamental to what we do.
The safety of the communities we operate in, our employees and the environment we live and work in is paramount. As a leading North American energy infrastructure company, our experience in building major export facilities off the West-Coast helps drive continued progress while being anchored by safety.
As AltaGas and Vopak partners to build this critical project, the teams on the ground stay committed to getting the project done, safely and reliably.
Stay Informed
As progress on the REEF project continues to roll out, we are committed to keeping our stakeholders and right holders up-to-date on project construction on a monthly basis.
Construction progress: September 18, 2025
September 18, 2025
Uplands:
- Continue rock placement and foundation backfilling
- Continue concrete foundations work
- Includes main plant area and interconnecting pipe rack foundations and Jetty
- Finalizing installation of underground Firewater and Electrical facilities
- Mechanical Contractor has mobilized and off to strong start setting modules and equipment
- Cold Storage building has been erected and work continues on the Warehouse and Office / Control Room buildings
Rail, Road and Utilities Corridor (RRUC):
- Continue with rock crushing and placement
- Continue with culvert and manhole install
- Rail construction is progressing on schedule as planned
Jetty Updates:
- Pier 1: Completed grout and ready to receive Trestle Span 1
- Pier 2: Completed grout and ready to receive Trestle Span 2
- Pier 3: Ready for grout
- Pier 4: Completed grout and ready for preparation of Trestle install
- Pier 5: Completed grout and ready for preparation of Trestle install
- Pier 6: Continue with rock socket drilling
- Pier 7: Permanent piles installed, ready for rock socket drilling
- Pier 8: Permanent piles installed, ready for rock socket drilling
- Pier 9: Ready for permanent pile cap install
- Pier 10: Drilling final permanent piles
- Pier 11: Ready for rock socket drilling
- Pier 12: Ready for rock socket drilling
- Loading Platform:
- LP-4: Falseworks piles/frame installed; prepping for permanent jacket install
- LP-6: Permanent piles installed; ready for rock socket
- LP-7/8: Permanent piles installed; ready for rock socket
- Trestle Module Spans 1 and 2 delivered and set into place September 3-6
- Offloaded last marine vessel load of remaining loading platform piles and jacket
Marine Offloading Facility (MOF):
- Completed installation of RRUC to MOF access ramp
- Wharf construction completed (by PRPA)
- First use was early September with the offloading of the Trestle span 1 and piperack modules for the Uplands area
- Asian fabrication status:
- REEF’s LPG Accumulators and Bullets for the project are 80% complete and are projected to start arriving onsite in October
- Interconnect pipe rack module fabrication is progressing per plan
- First shipment arrived early September with the second shipment in transit
Night activities:
- Night activities include water management, fueling, rock breaking on the west Rail, Road Utility Corridor and Uplands foundation backfill, and welding on the Jetty piers
- No active night drilling activities are occurring at night on site
Dust control:
- We are committed to maintaining safe on-site conditions that adhere to best practices
- We use freshwater for on-site road dewatering, to manage dust exposure and minimize impacts to the community
Port Edward Harbour Usage:
- Beginning mid-September, there will be an increase in traffic at the Port Edward Marina early in the morning and end of the day as four vessels will transport employees from Marina to the Jetty for work on the piers and loading platform. This will also result in more vehicles in parking areas.
Construction progress: August 20, 2025
August 20, 2025
Uplands:
- Drilling and blasting completed end of July
- Continue rock placement and foundation backfilling
- Continue concrete foundations work
- Includes main plant area and interconnecting pipe rack foundations and Jetty
- Continue installing underground Firewater and Electrical
- Mechanical Contractor is mobilized to site and started setting pipe rack modules
Rail, Road and Utilities Corridor (RRUC):
- Continue with rock crushing and placement
- Continue with culvert and manhole install
- Rail construction is progressing
Jetty Updates:
- Pier 1: Completed grout annulus
- Pier 2: Completed pile cap install and welding
- Pier 3: Preparation for pile cap installation
- Pier 4: Completed concrete infill
- Pier 6: Continue with rock socket drilling
- Pier 9: Pile cap welding in progress
- Pier 10: Continue work on permanent piles
- Loading Platform:
- LP-7/8: Falsework beams and jackets installed
- LP-6: Falseworks piles and frame installed
- Work continues to progress on other piers ranging from Pier 1 to Pier 10 and Loading Platform Piers 7 & 8 where we have completed deck/railings
- Trestle Module Spans 1 and 2 will be delivered to site the first week of September
- Offloaded last marine vessel load of loading platform piles and jackets completed
Marine Offloading Facility (MOF):
- Substantially completed installation of RRUC to MOF access ramp
- Wharf has been substantially completed by the PRPA with plans for first use in September 2025
Asian Fabrication Status:
- REEF’s LPG Accumulators and Bullets for the project are 80% complete and are projected to start arriving onsite in October
- Interconnect pipe rack module fabrication is progressing per plan with the first shipment in transit
Night Activities:
- Night activities include water management, fueling, rock breaking on the west Rail, Road Utility Corridor and Uplands foundation backfill, and welding on the Jetty piers
- No active night drilling activities are occurring at night on site
Dust Control:
- We are committed to maintaining safe on-site conditions that adhere to best practices
- We use freshwater for on-site road dewatering, to manage dust exposure and minimize impacts to the community
Construction progress: July 18, 2025
July 18, 2025
Uplands:
- Nearing completion with drilling and blasting
- Proactively being broken into smaller and more detailed segments
- Continue rock placement and foundation backfilling
- Continue concrete foundations work
- Includes main plant area and interconnecting pipe rack foundations and Jetty
- Continue installing underground Firewater and Electrical
- Mechanical Installation contract awarded and set to mobilize latter part of July
Rail, Road and Utilities Corridor (RRUC):
- Continue with rock crushing and placement, drilling and blasting
- Continue with culvert and manhole install
- Rail construction materials have started to arrive on site
- Rail construction continues
- Completed tie removal and replace program
- Outbound track construction in progress
Jetty Updates:
- Pier 1: Completed concrete infill and pile cap installation
- Pier 2: Completed rock socket drilling
- Pier 3: Completed rock socket drilling
- Pier 4: All four piles drilled successfully
- Pier 6: All four piles drilled successfully
- Pier 9: Welding occurring
- Pier 10: Permanent jacket installed
Loading Platform:
- LP-7/8: Permanent jackets installed
- LP-6: Falseworks piles and frame installed
- Work continues to progress on other piers ranging from Pier 1 to Pier 10 and Loading Platform Piers 7 & 8 where we have completed deck/railings have been completed
- Trestle Module Spans 1 and 2 will be delivered to site the first week of September
- Offloaded last marine vessel load of piles and jackets mid-July
Marine Offloading Facility (MOF):
- Substantially completed installation of RRUC to MOF access ramp
Asian Fabrication Status:
- REEF’s LPG Accumulators and Bullets for the project are 80% complete and are projected to start arriving onsite in September
Night Activities:
- Night activities include water management, fueling, rock breaking on the west RRUC and Uplands foundation backfill, and welding on the Jetty piers
- No active night drilling activities are occurring at night on site
Dust Control:
- We are committed to maintaining safe on-site conditions that adhere to best practices
- Use freshwater for on-site road dewatering, to manage dust exposure and minimize impacts to the community
© 2025 Ridley Island Energy Export Facility Limited Partnership. All Rights Reserved. | Last update: 2025_09_18