Construction Updates
See Advisory Statement for important information related to the climate and sustainability content on this website.
Safety
Safety is our number one value and is fundamental to what we do.
The safety of the communities we operate in, our employees and the environment we live and work in is paramount. As a leading North American energy infrastructure company, our experience in building major export facilities off the West-Coast helps drive continued progress while being anchored by safety.
As AltaGas and Vopak partners to build this critical project, the teams on the ground stay committed to getting the project done, safely and reliably.
Stay Informed
As progress on the REEF project continues to roll out, we are committed to keeping our stakeholders and right holders up-to-date on project construction on a monthly basis.
Construction progress: Apr. 17, 2025
Apr. 17, 2025
Uplands:
- Complete overburden removal.
- Continuing with drilling and blasting.
- Continue rock placement.
- Continue concrete foundations work.
- Includes forming, rebar placement, pouring etc.
Rail Road and Utilities Corridor (RRUC):
- Complete overburden removal.
- Continue with rock crushing and placement, drilling and blasting.
- Continue with culvert & manhole install.
- Preparing for rail construction mobilization in May.
Marine Updates:
- 5 derricks are fully mobilized and operational.
- Continuing work at Pier 1.
- Pier 10 continuing false works and temporary piles.
- Commenced drilling activities at Pier 3.
*A derrick is a lifting device used for moving materials vertically and horizontally.
Night shift activities:
- Concluded night shift activities on March 26.
Construction progress: Mar. 13, 2025
Mar. 13, 2025
Overburden Removal:
- Uplands:
- Continue with overburden rock removal and fill placement West and Centre and East.
- Continuing with rock drilling and blasting in work areas West, Centre and East.
Rail Road and Utilities Corridor (RRUC):
- Continue with overburden removal in East RRUC North, Centre and South.
- Continue with fill placement East RRUC North, Centre and South.
- Continue with rock crushing in North RRUC East.
- Started culvert installation.
Permanent Concrete Works:
- Continue with Balance of Plant (BOP) foundations work.
Marine Updates:
- Currently 4 Derricks* fully mobilized and operational.
- Continued with falsework frame and pile installation on Piers 4, 5, 6, 7 & 8.
*Derricks are lifting devices used for moving materials vertically and horizontally.
Night shift activities:
Night shift activities continue in support of overburden removal.
Construction progress: Feb. 18, 2025
Feb 18, 2025
Uplands:
- Continue with overburden removal and fill placement.
- Continuing with rock drilling and blasting in work areas.
Rail Road and Utilities Corridor (RRUC):
- Continue with overburden removal in North, East and South RRUC.
- Continue with fill placement East RRUC.
- Continue rock crushing and aggregate production.
- Rail offloading pedestals – Complete.
- Start 69 kV relocation scope.
Permanent concrete works:
- Continue with Balance of Plant (BOP) foundations work.
Marine updates:
- 3 Derricks are fully mobilized and operational.
- Continued with falsework frame & pile installation on Piers 4, 5, 6, 7 & 8.
Night shift activities:
To mitigate weather conditions and unforeseen challenges, the REEF project will begin night shift activities.
- Start Date: February 12, 2025
- Duration: 3-6 weeks
- Activity: Onshore civil construction
- Questions: Contact us
© 2025 Ridley Island Energy Export Facility Limited Partnership. All Rights Reserved. | Last update: 2025_04_17