Construction Updates
See Advisory Statement for important information related to the climate and sustainability content on this website.
Safety
Safety is our number one value and is fundamental to what we do.
The safety of the communities we operate in, our employees and the environment we live and work in is paramount. As a leading North American energy infrastructure company, our experience in building major export facilities off the West-Coast helps drive continued progress while being anchored by safety.
As AltaGas and Vopak partners to build this critical project, the teams on the ground stay committed to getting the project done, safely and reliably.
Stay Informed
As progress on the REEF project continues to roll out, we are committed to keeping our stakeholders and right holders up-to-date on project construction on a monthly basis.
Construction progress: February 23, 2026
February 23, 2026
Optimization One construction updates:
- Civil earthworks (overburden removal complete, excavation of foundations ongoing)
- Foundation formwork ongoing
Initial construction build out updates:
Uplands:
- Continue concrete foundations work, will complete last pour in February
- 110 modules successfully set; ~81% of modules set to date
- Mechanical Contractor making good progress on setting modules and equipment
- Electrical & Instrumentation achieving good progress on electrical scope and field erected buildings
Rail, Road and Utilities Corridor (RRUC):
- Rail offload modules continue to be set upon delivery, and fit ups are going well
- Rail contractor finalizing track surfacing E&I contractor making good progress on standing power poles, 154 poles stood to-date
- Blasting in ERRUC commencing early March and expected to last through April
Jetty Updates:
- Pier 1: Completed; Span 1 set
- Pier 2: Completed; Span 2 set
- Pier 3: Completed; Span 3 set
- Pier 4: Completed; Span 4 set
- Pier 5: Completed; Span 5 set
- Pier 6: Completed; Span 6 set
- Pier 7: Completed; Span 7 set
- Pier 8: Completed; Span 8 set
- Pier 9: Continuing welding pile caps & shims
- Pier 10: Continuing welding pile caps & shims
- Pier 11: Rock Socket 75% complete
- Pier 12: Concrete infill complete; ready for Pile Cap
- Loading Platform:
- LP-03: Temporary falseworks piles installed
- LP-04: Piles installed; ready for Rock Socket
- LP-05: Permanent piles stacked
- LP-6: Permanent Piles installed and ready for Rock Socket
- LP-7/8: Permanent piles stacked and 50% seated
- Recovery and salvage of crane boom from crane weather event at Pier 11 in progress
- Focus on completing piers 9-12 by end of January
- Spans 9-11 offloaded onto a barge and will be set in April
- Continued with Trestle Span module interconnect bolt up activity
Asian Fabrication Status:
- Remaining 2 Accumulators and final interconnecting modules ready to ship, installation pending until return of the Marine Transport vessel
Marine Offloading Facility (MOF):
- Continues to be used for offloading marine shipments as they arrive
- Fourth ship with the remaining Uplands pipe rack modules and Accumulators #2 and #3 to arrive in the following weeks
Watson Island Camp (near Port Edwards):
- Progress made on remediation and replacement post fire incident from Jan 2
- Temporary facilities brought in January to lessen burden on surrounding communities
- Replacement facilities on schedule to be operational by end of Feb / 1st week in March
Night Activities:
- AltaGas continued with some night shift activities for marine jetty construction
- Start Date: October 24, 2025
- End Date: June 2026
- Best efforts will be made to minimize potential noise and light impacts
- Activity: welding and scaffolding activities
- Questions: Contact us
Construction progress: January 21, 2026
January 21, 2026
Optimization One construction updates:
- Civil earthworks ongoing (overburden removal, excavation of foundations)
- Foundation formwork ongoing
Initial construction build out updates:
Uplands:
- Continue concrete foundations work
- 80 modules successfully set; ~80% of modules set to date
- Mechanical Contractor making good progress on setting modules and equipment
- Electrical & Instrumentation beginning work ramp up Achieving good progress on field erected buildings
Rail, Road and Utilities Corridor (RRUC):
- Rail offload modules continue to be set upon delivery and fit ups going well
- Rail contractor finalizing track surfacing E&I contractor making good progress on standing power poles, 118 poles stood to-date
Jetty Updates:
- Pier 1: Completed; Span 1 set
- Pier 2: Completed; Span 2 set
- Pier 3: Completed; Span 3 set
- Pier 4: Completed; Span 4 set
- Pier 5: Completed; Span 5 set
- Pier 6: Completed; Span 6 set
- Pier 7: Completed; Span 7 set
- Pier 8: Completed; Span 8 set
- Pier 9: Continuing welding pile caps & shims
- Pier 10: Continuing welding pile caps & shims
- Pier 11: Rock Socket 75% complete
- Pier 12: Concrete infill complete; ready for Pile Cap
- Loading Platform:
- LP-03: Temporary falseworks piles installed
- LP-04: Piles installed; ready for Rock Socket
- LP-05: Permanent piles stacked
- LP-6: Permanent Piles installed and ready for Rock Socket
- LP-7/8: Permanent piles stacked and 50% seated
- Recovery and salvage of crane boom from crane weather event at Pier 11 in progress
- Focus on completing piers 9-12 by end of January
- Spans 9-11 offloaded onto a barge and will be set in April
- Continued with Trestle Span module interconnect bolt up activity
Asian Fabrication Status:
- Remaining 2 Accumulators and final interconnecting modules ready to ship, installation pending until return of the Marine Transport vessel
Marine Offloading Facility (MOF):
- Continues to be used for offloading marine shipments as they arrive
- Fourth ship with the remaining Uplands pipe rack modules and Accumulators #2 and #3 to arrive February 2026
Night Activities:
- AltaGas continued with some night shift activities for marine jetty construction.
- Start Date: October 24, 2025
- End Date: June 2026
- Best efforts will be made to minimize potential noise and light impacts
- Activity: welding and scaffolding activities
- Questions: Contact us
Construction progress: December 20, 2025
December 20, 2025
Optimization One construction updates:
- Civil earthworks ongoing (overburden removal, excavation of foundations)
- Foundation formwork commenced
Initial construction build out updates:
Uplands:
- Continue concrete foundations work
- 85 modules successfully set in the last two months; 90% off modules set to date
- Mechanical Contractor making good progress on setting modules and equipment
- Electrical & Instrumentation progressing well on material orders and delivery to enable work ramp up in the new year
- Achieving good progress on field erected buildings
Rail, Road and Utilities Corridor (RRUC):
- Rail offload modules continue to be set upon delivery and fit ups going well
- Rail contractor wrapping up track surfacing and will return in mid-2026 to complete
- E&I contractor making good progress on standing power poles
Jetty Updates:
- Pier 1: Completed; Span 1 set
- Pier 2: Completed; Span 2 set
- Pier 3: Completed; Span 3 set
- Pier 4: Completed; Span 4 set
- Pier 5: Completed; Span 5 set
- Pier 6: Completed; Span 6 set
- Pier 7: Turned over to AltaGas
- Pier 8: Turned over to AltaGas
- Pier 9: Ready to Set Permanent Jacket
- Pier 10: Ready to Set Permanent Jacket
- Pier 11: Rock Socket 75% complete
- Pier 12: Ready for Concrete Infill
- Loading Platform:
- LP-03: Temporary falseworks piles installed
- LP-04: Falseworks piles and frame installed
- LP-05: Permanent piles stacked
- LP-6: Permanent Piles stacked
- LP-7/8: Permanent piles stacked and sealed
- Focus on completing piers 9-12 to set Trestle Span module early January
- Welding to restart on Piers 9-11 December 28 with full activities resuming January 5
- Continued with Trestle Span module interconnect bolt up activity
Asian Fabrication Status:
- REEF’s LPG Accumulators and Bullets and more modules arrived November 15;
- Remaining 2 Accumulators and final interconnecting modules ready to ship pending return of the Marine Transport vessel
Marine Offloading Facility (MOF):
- Continues to be used for offloading marine shipments as they arrive
- Fourth ship with the remaining Uplands pipe rack modules and Accumulators #2 and #3 to arrive end of January 2026
Night Activities:
- AltaGas continued with some night shift activities for marine jetty construction.
- Start Date: October 24, 2025
- End Date: June 2026
- Best efforts will be made to minimize potential noise and light impacts
- Activity: welding and scaffolding activities
- Questions: Contact us
© 2026 Ridley Island Energy Export Facility Limited Partnership. All Rights Reserved. | Last update: 2026_02_24

