Construction Updates
See Advisory Statement for important information related to the climate and sustainability content on this website.
Safety
Safety is our number one value and is fundamental to what we do.
The safety of the communities we operate in, our employees and the environment we live and work in is paramount. As a leading North American energy infrastructure company, our experience in building major export facilities off the West-Coast helps drive continued progress while being anchored by safety.
As AltaGas and Vopak partners to build this critical project, the teams on the ground stay committed to getting the project done, safely and reliably.
Stay Informed
As progress on the REEF project continues to roll out, we are committed to keeping our stakeholders and right holders up-to-date on project construction on a monthly basis.
Construction progress: December 20, 2025
December 20, 2025
Optimization One construction updates:
- Civil earthworks ongoing (overburden removal, excavation of foundations)
- Foundation formwork commenced
Initial construction build out updates:
Uplands:
- Continue concrete foundations work
- 85 modules successfully set in the last two months; 90% off modules set to date
- Mechanical Contractor making good progress on setting modules and equipment
- Electrical & Instrumentation progressing well on material orders and delivery to enable work ramp up in the new year
- Achieving good progress on field erected buildings
Rail, Road and Utilities Corridor (RRUC):
- Rail offload modules continue to be set upon delivery and fit ups going well
- Rail contractor wrapping up track surfacing and will return in mid-2026 to complete
- E&I contractor making good progress on standing power poles
Jetty Updates:
- Pier 1: Completed; Span 1 set
- Pier 2: Completed; Span 2 set
- Pier 3: Completed; Span 3 set
- Pier 4: Completed; Span 4 set
- Pier 5: Completed; Span 5 set
- Pier 6: Completed; Span 6 set
- Pier 7: Turned over to AltaGas
- Pier 8: Turned over to AltaGAs
- Pier 9: Ready to Set Permanent Jacket
- Pier 10: Ready to Set Permanent Jacket
- Pier 11: Rock Socket 75% complete
- Pier 12: Ready for Concrete Infill
- Loading Platform:
- LP-03: Temporary falseworks piles installed
- LP-04: Falseworks piles and frame installed
- LP-05: Permanent piles stacked
- LP-6: Permanent Piles stacked
- LP-7/8: Permanent piles stacked and sealed
- Focus on completing piers 9-12 to set Trestle Span module early January
- Welding to restart on Piers 9-11 December 28 with full activities resuming January 5
- Continued with Trestle Span module interconnect bolt up activity
Asian Fabrication Status:
- REEF’s LPG Accumulators and Bullets and more modules arrived November 15;
- Remaining 2 Accumulators and final interconnecting modules ready to ship pending return of the Marine Transport vessel
Marine Offloading Facility (MOF):
- Continues to be used for offloading marine shipments as they arrive
- Fourth ship with the remaining Uplands pipe rack modules and Accumulators #2 and #3 to arrive end of January 2026
Night Activities:
- AltaGas continued with some night shift activities for marine jetty construction.
- Start Date: October 24, 2025
- End Date: June 2026
- Best efforts will be made to minimize potential noise and light impacts
- Activity: welding and scaffolding activities
- Questions: Contact us
Construction progress: November 18, 2025
November 18, 2025
Optimization One construction updates:
Optimization 1 Project:
- Civil earthworks has commenced (tree clearing, overburden removal)
Initial construction build out updates:
Uplands:
- Continue concrete foundations work
- Mechanical Contractor making good progress on setting modules and equipment
- Electrical & Instrumentation Contractor work ongoing
- Achieving good progress on field erected buildings
Rail, Road and Utilities Corridor (RRUC):
- Rail contractor will return in mid-2026 to complete
Jetty Updates:
- Pier 1: Completed; Span 1 set
- Pier 2: Completed; Span 2 set
- Pier 3: Completed; Span 3 set
- Pier 4: Completed; Span 4 set
- Pier 5: Completed; Span 5 set
- Pier 6: Completed; Span 6 set
- Pier 7: Turned over to AltaGas
- Pier 8: Turned over to AltaGAs
- Pier 9: Ready for concrete infill
- Pier 10: Concrete infill in progress
- Pier 11: Ready for Rock socket
- Pier 12: Permanent piles stacked
- Loading Platform:
- LP-03: Temporary falseworks piles installed
- LP-04: Falseworks piles and frame installed
- LP-05: Permanent piles stacked
- LP-6: Permanent Piles stacked
- LP-7/8: Permanent piles stacked and sealed
- Trestle Module Spans 3 and 6 set in place at the end of October
Asian Fabrication Status:
- REEF’s LPG Accumulators and Bullets and more modules arrived November 15; off loading in progress
Marine Offloading Facility (MOF):
- Continues to be used for offloading marine shipments as they arrive
- Third ship has docked at the MOF and currently unloading the first Accumulator, 2 Bullets, and some more modules from Asia
Night Activities:
- AltaGas continued with some night shift activities for marine jetty construction.
- Start Date: October 24, 2025
- End Date: June 2026
- Best efforts will be made to minimize potential noise and light impacts.
- Activity: Additional activities will include drilling, welding and scaffolding activities .
- Questions: Contact us
Construction progress: October 18, 2025
October 18, 2025
Updated November 6, 2025
Uplands:
- Continue rock placement and foundation backfilling
- Continue concrete foundations work
- Mechanical Contractor continuing work on setting modules and equipment
- Electrical & Instrumentation Contractor awarded and scope to begin ramping up at site
- Achieving good progress on field erected buildings
- Additional tree clearing activity will start on November 10 and will occur for approximately 4-6 weeks
Rail, Road and Utilities Corridor (RRUC):
- Rock crushing completed on available material
- Rail construction will wrap up 2025 work in Q3 and return in mid-2026 to complete
Jetty Updates:
- Pier 1: Completed; Span 1 set
- Pier 2: Completed; Span 2 set
- Pier 3: Turned over to AltaGas
- Pier 4: Turned over to AltaGas
- Pier 5: Turned over to AltaGas
- Pier 6: Turned over to AltaGas
- Pier 7: Turned over to AltaGas
- Pier 8: Grout complete
- Pier 9: One rock socket remaining
- Pier 10: One rock socket remaining
- Pier 11: Ready for Rock socket
- Pier 12: Permanent piles stacked
- Loading Platform:
- LP-7/8: Permanent piles stacked and sealed
- LP-6: Permanent Piles stacked
- LP-5: Falseworks piles and frame installed
- LP-4: Falseworks piles and frame installed
- Trestle Module Spans 3 and 6 will be delivered to site by the end of October
Marine Offloading Facility (MOF):
- Ready to receive next shipments
- Second ship has docked at the MOF and currently unloading 43 modules from Asia
Asian Fabrication Status:
- REEF’s LPG Accumulators and Bullets for the project are complete and are projected to start arriving onsite in 1st week in November
Night Activities:
- AltaGas will be commencing with some additional night shift activities for marine jetty construction.
- Best efforts will be made to minimize potential noise and light impacts.
- Start Date: October 24, 2025
- End Date: June 2026
- Activity: Additional activities will include drilling. Welding and scaffolding activities will continue.
- Questions: Contact us
© 2025 Ridley Island Energy Export Facility Limited Partnership. All Rights Reserved. | Last update: 2025_11_20

