Construction Updates
See Advisory Statement for important information related to the climate and sustainability content on this website.
Safety
Safety is our number one value and is fundamental to what we do.
The safety of the communities we operate in, our employees and the environment we live and work in is paramount. As a leading North American energy infrastructure company, our experience in building major export facilities off the West-Coast helps drive continued progress while being anchored by safety.
As AltaGas and Vopak partners to build this critical project, the teams on the ground stay committed to getting the project done, safely and reliably.
Stay Informed
As progress on the REEF project continues to roll out, we are committed to keeping our stakeholders and right holders up-to-date on project construction on a monthly basis.
Construction progress: June 20, 2025
June 20, 2025
Uplands:
- Continuing with drilling and blasting.
- Proactively being broken into smaller and more detailed segments.
- Continue rock placement and foundation backfilling.
- Continue concrete foundations work.
- Includes main plant area and interconnecting pipe rack foundations and Jetty.
Rail Road and Utilities Corridor (RRUC):
- Continue with rock crushing and placement, drilling and blasting.
- Continue with culvert and manhole install.
- Rail construction materials have started to arrive on site.
- Construction underway with tie removal and replace program nearing completion.
Jetty Updates:
- Pier 1: Continue permanent pile drilling.
- Pier 3: Rock Socket drilling.
- Pier 4: All four piles drilled successfully.
- Pier 6: All four piles drilled successfully.
- Pier 9: Welding occurring.
- Pier 10: Permanent jacket installed.
Work continues to progress on other piers ranging from Pier 1 to Pier 10 and Loading Platform Piers 7 & 8 where we have completed deck/railings.
Marine Offloading Facility (MOF):
- Continue installation of RRUC to MOF access ramp.
Asian Fabrication Status:
- REEF’s LPG Accumulators and bullets for the project are 80% complete and are projected to start arriving onsite in September.
Night Drilling Activities:
- Night activities include water management, fueling, rock breaking west RRUC and uplands foundation backfill.
- No active night drilling activities is occurring on site.
Dust Control:
- We are committed to maintaining safe on-site conditions that adhere to best practices. To manage dust exposure and minimize impacts to the community, we use freshwater for on-site road dewatering.
Construction progress: May 20, 2025
May 20, 2025
Uplands:
- Completed drilling and blasting in the coming weeks.
- Continue rock placement.
- Continue concrete foundations work.
- Includes main plant area and interconnecting pipe rack foundations.
Rail Road and Utilities Corridor (RRUC):
- Continue with drilling, blasting, rock crushing, and placement.
- Continue with culvert and manhole install.
- Rail construction materials have started to arrive on site. Construction to begin early June.
Marine Offloading Facility (MOF):
- Started installation of RRUC to MOF access ramp.
Jetty Updates:
- Pier 1: Continue permanent pile drilling.
- Pier 4: All four piles drilled successfully.
- Pier 6: All four piles drilled successfully.
Asian Fabrication Status:
- REEF’s LPG Accumulators and bullets for the project are over 70% complete and are projected to start arriving onsite in August. More here »
Construction progress: Apr. 17, 2025
Apr. 17, 2025
Uplands:
- Complete overburden removal.
- Continuing with drilling and blasting.
- Continue rock placement.
- Continue concrete foundations work.
- Includes forming, rebar placement, pouring etc.
Rail Road and Utilities Corridor (RRUC):
- Complete overburden removal.
- Continue with rock crushing and placement, drilling and blasting.
- Continue with culvert & manhole install.
- Preparing for rail construction mobilization in May.
Marine Updates:
- 5 derricks are fully mobilized and operational.
- Continuing work at Pier 1.
- Pier 10 continuing false works and temporary piles.
- Commenced drilling activities at Pier 3.
*A derrick is a lifting device used for moving materials vertically and horizontally.
Night shift activities:
- Concluded night shift activities on March 26.
© 2025 Ridley Island Energy Export Facility Limited Partnership. All Rights Reserved. | Last update: 2025_06_20